Plans and forecasts

Gazprom Holding plans to commission the first startup complex at the Amur Gas Processing Plant in Q2 2021. In total, the plant provides for 5 start-up complexes and 6 technological lines with the capacity of 7 billion cubic meters each. The remaining lines will be launched sequentially until 2025. The capacity is to reach 42 billion cubic meters of gas per year.
Gazprom
Gazprom
Review
Source: tass.ru
  • BlackTerminal.com 2016 - 2026.