At the Nadezhda Metallurgical Plant of Nornickel completed one of the most difficult types of work - refractory lining of the basement and wall. By the end of this week, installation of another three kilometers of copper pipeline and cable lines will be completed. After that, the plant will begin preparations for equipment commissioning. The new furnace is scheduled to heat up on July 16, three days ahead of schedule.