On the boiler unit No.3 of Berezovskaya GRES after completion of repair works and cold adjustment of the equipment, the first ignition with a step-by-step increase in heat capacity up to 30% was carried out. This step marked the beginning of the steam and oxygen cleaning and passivation program which will continue for about two weeks. Its successful completion will allow us to enter the final stage of the power unit overhaul.