Nizhnekamskneftekhim started testing of high-pressure boilers at the pyrolysis, compression and gas separation production facilities of the EP-600 ethylene complex under construction. In addition, commissioning works are already underway on several auxiliary production systems. On the main main pyrogas compressor, commissioning work will start in the second quarter of 2024. Overall progress on the project to date is already 87.48%.