Enel Russia may delay the commissioning of the Azov WPP with the capacity of 90 MW for several months. The reason is the problem of movement of specialists for the installation of equipment due to closure of borders, as well as difficulties with the supply of components. Technical work on the project will be completed by the end of the year, says the financial director Yuliya Matyushova. The power plant is being built according to the PDM and the rules of the contract, fines are provided for the failure of the launch date.