First production line of the Arctic LNG-2 plant was 95% complete at the end of last year. Overall progress of the project was 73%. At the production facility in the Murmansk region, the installation of modules was completed and hydraulic tests of the gravity base of the first line were carried out. Commissioning operations are underway. And concrete work has been completed on the second line's OGT platform, and mechanical equipment is being installed.