Construction schedule of the Murmansk LNG terminal in the Kola Bay of the Barents Sea has been adjusted and the completion of works has been postponed from 2033 to 2030, as follows from the materials of the preliminary environmental impact assessment submitted for public discussions. Construction will be divided into six phases. First stage will last from 2027 to 2029. Second - from 2028 to 2029. Third, fifth and sixth phases - from 2027 to 2030. Fourth phase - from 2029 to 2030.