MMC Norilsk Nickel will be forced to push back the construction of the new Norilsk Concentrator and the third smelting complex at the Nadezhda Metallurgical Plant by at least two years. Feadlines are being pushed back due to the need to replace suppliers of equipment and components, as well as problems with the availability of financing. However, more than a half of Nornickel's programs for 2023 are not related to the supply of high-tech equipment. For example, this year, it is planned to complete the Northern Project 2.0 phase, ramp up production at Bear Creek, and implement two or three other medium-sized projects.